MGT-440 Project management

MGT-440 Project management

Reread the Kitchen Heaven Project Case Study in Heldman et al. pages 84-87, 139-141, 190-193, and 283-285.
Part 1: Action Steps

For each activity listed in the Action Steps section in the Logical Framework template complete the Resources, Budget (if given in the case), and Due Dates.

Add anticipated resources for each action step/activity. Include all types of resources including human, technical, and physical resources.
Add budget information as provided in the case. If budget information not specifically provided in the case, no budget information is required.

Estimate potential due dates for each action step/activity. These estimates should support the planned/expected end date of the project as defined in the case. Document assumptions made in setting the due dates.
Part 2: RACI Matrix
Complete the RACI Matrix Template. Add rows as needed.
Each action step/activity must be listed in the RACI matrix.

Part 3: PowerPoint Presentation (please create the slide show with detailed notes and I will do the voice over)
Create a short 3-minute presentation discussing the final Logical Framework and how the proposal meets the Goals presented in the­­­ case.
Responsible
Accountable
Consulted
Informed
Project Activities
Outcome 1
Outcome 2
Outcome 3
How to Use the RACI Matrix Template
The RACI matrix template is tool to help everyone in the project know what
their role is, so they can work better together.
Step 1: List the Project Tasks
In column 1, beneath the “Project Tasks” header, you will list all of the tasks
that will be completed as part of this project. In our example, we broke the
tasks down into the different project phases in order to keep things more
organized. If you wish, you can remove the project phases and instead just do
a large list of tasks, but we’ve found the project phases to be helpful.
Step 2: List All of Your Team Members
Next, locate the light blue bar. Going from left to right, we are going to add all
of your team members to this section. Include every person in your
organization, even if they won’t be working directly on the project, because
stakeholders are an important part of this document too. We find it helpful to
use the job title / role in this section, but you could also use team member
names instead. We tend to use job titles so that this document is useful to
someone looking at the matrix who may not be familiar with everybody’s
name.
Step 3: Assign R,A,C,I to Each Task
Locate your first task of the project (this should be whichever task you have
listed highest in Column A.) Once you’ve located your first task, move across
the matrix to the right, deciding who will be (R) Responsible for executing the
work on this particular task. Remember, R is for the person who will actually
be performing the work on this task.
Continue moving to the right, and next you will choose who will be (A)
Accountable for this task. The person who you label as (A) Accountable is the
person who will be responsible for ensuring that the task is done properly and
in a timely manner.
Next, you will decide who will be (C) Consulted on this task. Remember, (C)
means that a person will be asked for help or advice on a task, and they will
work with the responsible team member to complete the task. In some cases,
you will not have a C for a task and that’s OK.
Finally, for each task you will decide who is the stakeholder for the task. The
stakeholder will be labeled as (I) Informed. If someone is labeled (I) for this
task, they will be updated about the progress of the task, but they will not
have direct feedback going back to the person responsible for the task. An
informed person is a one way communication, as compared to a consulted
person who has two-way communication about the task. Most tasks will have
an informed person, however there will be some cases where there is no I
needed.
Step 4: Share the Document
Once your RACI chart is fully filled out, it is important to share the document
with all of the team members on this project. This is an important step
because a RACI matrix is most helpful when each team member understands
exactly what their role is at each step of the project.
Responsible
Accountable
Consulted
Informed
Project Tasks
Initiation Phase
Financial Study
Feasability Study
Planning Phase
Technology Recommendations
Financial Plan
Sprint Plan
Execution Phase
Design UI
Write Content
Create Mockup
Control Phase
User Testing
Close Phase
Create Lessons Learned
Create Closure Report
Product
Manager
UI Designer
Content Writer
Financial
Analyst
R
R
R
R
R
R
R
R
R
R
R
C
Design Director VP of Product
VP of Design
CTO
CEO
I
I
I
I
C
I
I
A
I
I
I
I
A
A
C
I
I
I
I
I
A
I
I
I
A
A
I
I
I
A
A
C
A
A
A
I
Logical Framwork for
Objectives
Goal:
Open a new Kitchen Heaven store in Colorado
Springs within six months.
3
Purpose:
To meet the demand for a Kitchen Heaven store
in the Colorado Springs area.
Outcomes:
Successful opening of the new store, increase
performance in the market, and the company’s
increased presence in the Colorado Springs area.
Inputs:
Manpower, supplies and materials, permits and
approvals, and a suitable location for the new
store.
Success Measures
Verification
Complete the project set up within 6 months.
Generate positive return. Meet the estimated
budget of $2 million.
Give project reports. Conduct project
reviews. Track project plan and
schedule.
The success measure of the purpose will be the
store’s performance in the market.
Conducted through monitoring and
analyzing the store’s sales figures and
customer feedback.
Success measure of the outcomes will be the
successful opening and performance of the new
store, increased customer base and sales, timely
completion of the project and staying within the
budget.
Regular monitoring and analysis of sales
figures, customer feedback, The team
will also review the project progress
and track it against the project plan and
schedule.
The project budget of $2 million Monitor and track any deviations,
to be obtained through the
shortages f supplies, and delays to
company’s financing and
ensure project outcomes are achieved.
managed by the project
manager.
page 1 of 6
Logical Framwork for
Objectives
Action Steps
Successful opening of the new store (Outcome
No.1)
5 Action Step
Verification
Success Measures
Resource
1. Identify and secure a suitable location for the
new store
Site visit,
transportation,
logistics, move
2. Negotiate to come to an agreement
Facilitation fee,
stakeholders.
3. Making necessary payments to secure the
location
Funds
4. Obtaining permits and approvals
Business
licenses, safey
permits, and
building permits.
5. Make follow ups to obtain the approvals and
business permits
Business
documents.
Budget
Due Dates
Successful perfromance in the market(Oucome
No.2)
5 Action Steps
page 2 of 6
Logical Framwork for
Objectives
1.Hiring the new staff
2.Stocking the store with inventory including
purchase, transportation and workforce
Success Measures
Store managers,
sales associates,
and support
staff.
Proper stocking
of kitchenware.
3.Launching the stores
Marketing
Marketing
materials: flyers,
brochures,
business cards.
Advertising the store in the new area
Social media,
email marketing,
and online
advertising.
Provision of excellent customer service
Training, funds.
page 3 of 6
Verification
Logical Framwork for
Assumptions
To reach Goal:
Identify and secure a suitable location for the new store. This will
require market research and scouting the area for potential
storefronts. Purchase and stocking the store with inventory.
There will be no other major events to grand shows taking place in
the same day for other companies during the Kitchen Heaven Store
opening date
The signing of the lease will have already taken place.
There will be enough funds to finance all the new products.
To reach Purpose:
Careful planning and execution of all necessary tasks and activities,
such as securing a suitable location, obtaining permits, hiring new
staff, and stocking the store with inventory.
The lease agreement should already e signed. New line of gourmet
food products will be available to meet the market demand.
Shelving should be executed as planned for better display of
products.
To produce Outcomes:
Ensure that the project objectives align with the company’s goals
and strategy. The project team will have to successfully execute all
the planned tasks and activities outlined in the project charter.
To obtain & manage Inputs:
Ensure project does not exceed the budget, manage workforce.
Supplies and materials to be utilized effectively. .
page 4 of 6
Logical Framwork for
Assumptions
1.Ensure that all stakeholdersattend meetings as required.
2.The lease agreement signed and all required linceses issued.
3.Cooking demos made available on the granding opining date.
4.Approval of the budget and regulation of finances.
5.Coordination of the grand opening of the store to ensure
efficiency.
Market research has been done on the neighborhood to determine
the safest and most suitable location for the store.
The location has been identified and negotiations are being done for
a suitable agreement.
Necessary payments for rent and security deposit are set aside to
secure the location.
The local authorities are aware of the new business sore being
opened in the area.
Follow ups with the appropriate agencies and authorites are being
done to avoid delays.
page 5 of 6
Logical Framwork for
Assumptions
Background checks have been conducted to ensure qualified and
trustworthy employees.
Market research has been conducted to determine the demand for
different products in the area.
The store is well stocked and ready to be lauched in the new area.
The store has unique features and products to stand out in the new
area.
The new staff are well trained to provide excellent customer service.
page 6 of 6

Purchase answer to see full
attachment

Order Solution Now

Our Service Charter

1. Professional & Expert Writers: Homework Free only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Homework Free are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Homework Free is known for timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Homework Free, we have put in place a team of experts who answer to all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.

Homework Free Org

Your one stop solution for all your online studies solutions. Hire some of the world's highly rated writers to handle your writing assignments. And guess what, you don't have to break the bank.

© 2020 Homework Free Org